Hi All,
Thanks in Advance..
I have a item FG0001A, Site x1 and in item coverage the minimum quantity defined as 30000 and coverage method is period for 27 days, positive days of 365 and negative days of 7, coverage time fence of 365 and enabled with "Strick safety stock" in coverage group.
Demand forecast is defined for every monday.
With Finite capacity enabled, when MRP run, system is suggesting the safety stock first as of today to produce which is required after 4 months and then the remaining orders for balance net required demand forecast.
So, may I know why it is like this and solution to avoid considering the safety stock and consider net required demand forecast ..?