Production floor execution

editSubscribe (0) ShareShare
ReportReport
Posted on by
I want to use production floor execution without using time and attendance 
How can I do that? 
Categories:
Attachments
  • Production floor execution
    Thank you ColbyGallagher , that what I was afraid of

    Thank you Andre Arnaud de Cal... 
    To answer your question why do I need to run production floor execution without using time and attendance:
    I want to use production floor execution to:

    schedule jobs, and use these jobs on master planning, and view progress, and view capacity and progress on Gantt chart.

    What I don't want to do is before ending the production order I have to : enter absence, clock out workers, fix lines errors then calculate, approve transfer for every worker, spending time in a task that has zero value for our organization
  • Suggested answer
    Production floor execution
    This is not currently possible, but may be allowed in a future release from what I have heard.  Its a pretty common request.  
  • Andre Arnaud de Calavon Profile Picture
    Andre Arnaud de Cal... Super User on at
    Production floor execution
    Hi,
     
    Can you explain how your envisioned process should work in the application? In case you don't want to use the specific features, can't you then just use the production journals?
  • Production floor execution
    Thanks Kevin Xia 
     
    But I don't need any of that 
    * I don't need clock in/out
    *  I don't need job to submit records to the time registries 
    * I don't need to fix the time registries errors, absence reason, etc
    Actually I don't want to use time &attendance at all

    Oll what I want is production floor execution without time and attendance kick-in 
     
  • Suggested answer
    Kevin Xia Profile Picture
    Kevin Xia Microsoft Employee on at
    Production floor execution
    Hi,
    You can refer to this official document: Configure the production floor execution interface - Supply Chain Management | Dynamics 365 | Microsoft LearnWhen you open the production floor execution interface, it automatically loads a selected configuration and job filter that are specific to the browser and device. In the configuration, you set the policies that must be applicable for a specific usage. Here are some usage examples:
    • On a device in the company hall, employees clock in when they come into the office, and they clock out when they leave for the day.
    • On a device on the shop floor, machine operators register when they start and complete jobs. They also register breaks and indirect activities.
    You can check whether you can cancel related settings.
    Best regards,
    Kevin

Helpful resources

Quick Links

New Blog Features Released!

Check out the new community blog features for viewers and authors…

Setting Up Knowledge Sources for Copilot…

Look at how configuring a comprehensive knowledge base is crucial…

Demystifying Copilot with Georg Glantschnig…

Industry experts answer burning questions directly from our amazing Community…

Featured topics

Product updates

Dynamics 365 release plans