Want to assign a resource with type Machine to the WBS projects Activity

editSubscribe (1) ShareShare
ReportReport
Posted on by
I Want to assign a resource with type Machine to the WBS projects Activity, What is the way to do that?
 
 
Categories:
Attachments
  • Graham K Profile Picture
    Graham K on at
    Want to assign a resource with type Machine to the WBS projects Activity
    Have you tested the following;
    Create Resource roles for each of the various types of machines -  
    Create the individual Resources by using the Individual Machine ID's- (In other words these workers just happen to be Machines)
     
    Then when you are scheduling in the WBS you can assign the Resource just as you would for a worker.
    If this works, it may also give you reporting on Utilization especially if you set up the correct working calendar's for them.
     
    Obviously this option is dependent on what other modules you are using such as Payroll and Human resources, but if you have a very basic OOTB config it may be worth testing.
  • Sukrut Parab Profile Picture
    Sukrut Parab on at
    Want to assign a resource with type Machine to the WBS projects Activity
    Maybe you can assign it as a skill to resource? and resource belongs to specific team which has that skill? 
  • Islam Mohab Profile Picture
    Islam Mohab on at
    Want to assign a resource with type Machine to the WBS projects Activity
    Sir thanks,
     
    It's a construction business so they have about 1000 machines and assign those machines to the project activity because it has cost and also integrated with Asset management so their is some downtime for breakdown or for preventive maintenance.
  • Andre Arnaud de Calavon Profile Picture
    Andre Arnaud de Cal... Super User on at
    Want to assign a resource with type Machine to the WBS projects Activity
    Hi Islam,
     
    I have never heard of this specific requirement before. I don't think the WBS will accept resources with this type of machine as it is all labor-focused. Can you explain the process for this business requirement?

Helpful resources

Quick Links

New Blog Features Released!

Check out the new community blog features for viewers and authors…

Setting Up Knowledge Sources for Copilot…

Look at how configuring a comprehensive knowledge base is crucial…

Demystifying Copilot with Georg Glantschnig…

Industry experts answer burning questions directly from our amazing Community…

Featured topics

Product updates

Dynamics 365 release plans